EN
FR

Road Work

At its regular meeting on February 1, 2021, Municipal Council has approved a list of maintenance and improvement projects to be carried out on municipal roads and other infrastructure in 2021. These projects will be carried out based on available monies and priorities established on the basis of:

  • Public safety issues
  • Road drainage
  • Grading set out in the 2009–2014 contingency plan by the outside firm
  • Work required as a result of the 2017 and 2019 floods
  • Short- and medium-term development projects
Note: Municipal Council can change the work plan depending on circumstances, emergencies, other considerations or opportunities.

      Ongoing and coming roads works





            Update on external work as of July 30

            ROADS AND PROJECTS

            STATUS OF WORK

            Chemin Clark

            Curve correction

            Work has been suspended for additional expertise required to ensure the stability of the rock walls for site and future users' safety. The resumption of work is scheduled no later than August 23, but excavation and clearing work could be done before then.

            Chemin Riverside

            Refection

            Modifications to the project following new environmental regulations («  Règlement sur l’encadrement d’activités en fonction de leur impact sur l’environnement » ) that have resulted in additional delays. Work will begin in the fall upon receipt of the required authorizations from ministère de l’Environnement et de la Lutte contre les changements climatiques (MELCC).

            The rehabilitation work, including stabilization, excavation, drainage, and paving, should be completed in the summer of 2022.

            Ministère des Transports du Québec is extending the construction period to summer 2022 (the municipality got close to $2.5 million in funding from the Quebec government for this project.

            Gauvreau-Labelle Project

            Drainage improvement

            Drainage design underway and should be completed by fall.

            Chemin Kennedy

            Culvert replacement

            The call for tenders to award the contract is underway. Work is scheduled to begin this year, subject to receipt of the certificate of authorization from MELCC.

            Chemin Mclinton and Mill

            Slope stabilization

            Call for tenders underway and work planned before next winter

            Various roads (Kennedy, des Érables, Vieux-Pont, de la Rivière and others)

            Culverts replacement, paving and repair, and installation of guardrails

            Preparation in progress: sizing of culverts, plans and specifications, calls for tenders.




            Ongoing work by the Ministère des Transports du Québec (MTQ)

              Completed works 

                • Chemin Riverside, between Chemin Burnside and Chemin Sully : paving and marking work  carried out from Friday, May 22 to Monday 25.
                • Chemin de la Batteuse: Shoreline stabilization work scheduled for mid-March, between civic numbers 22 and 34. Paving work will be done at a later date during the year 2020.
                • Chemin Montée Beausoleil : between 429 and 669 from June 17 to 25, 2020 for culvert replacement work.
                • From July 20 to 31 2020
                • August 2020
                • September 2020
                • Octobre 2020
                • November 2020
                • May-August 2021


                    Last update : September 11, 2021